Commercial Farmers' Union of Zimbabwe

Commercial Farmers' Union of Zimbabwe

***The views expressed in the articles published on this website DO NOT necessarily express the views of the Commercial Farmers' Union.***

More power outages loom

More power outages loom

http://www.theindependent.co.zw/

Thursday, 06 October 2011 16:34

Chris Muronzi

ZIMBABWE is headed for more power outages after several generation units at 
the country’s most reliable power station, Kariba,  went off owing to 
various faults, a Zimbabwe Power Company report to industry says.

According to the report, Kariba, which has largely been operating at full 
capacity for the past two years, is struggling.

“During the week ending 25th September the protection on Units 3 and 4 
tripped. Unit 4 was isolated from the transformer which it shares with Unit 
3. Unit 3 was then brought back into service. After meticulous trouble 
shooting, it was found that switchgear and control devices, which were 
replaced by another OEM (Original Equipment Manufacturer) during our 
maintenance shutdowns earlier this year, had failed. Repairs to these 
devices are underway under guidance of the OEM from Europe,” said the 
report.

The problems at Kariba Power Station started in June after a failure in the 
generator winding of Unit 2.

Copper windings to get Unit 2 back on stream can only be manufactured and 
fitted by OEM.

The problem was compounded by a crack that was found in one of the turbine 
blades which only the OEM can repair.

“This repair work is underway and is scheduled for completion before 
mid-October. In my view the OEM did not, and could not, be encouraged to 
respond to our crisis with the urgency demanded by our unique situation or 
with the respect that a 30year relationship deserves. Our MD has been in 
Europe this week to discuss this with the OEM,” said the report.

ZPC foresees a “significant amount of work” going into stabilising Hwange 
Power Station and hopes to float a tender once funding becomes available to 
replace key components which have lead times of up to one year.

Hwange, according to the report, lost four Phase One smaller units over the 
last week.

“ Unit 1 due to the failure of the “Boiler Feed Pump” which is new and under 
warranty, Unit 2 due to a failure of its thrust bearing, Unit 3 due to wear 
on its induction fans caused by the under-performing de-ashing system and 
Unit 4 due to the failure of its Boiler Feed Pump,” said the report.
The problems at Hwange were worsened after the entire station was taken out 
by a surge out of Eskom last Tuesday.
“At the time of writing this statement we now have two Phase Two (larger) 
units and one Phase One (smaller) unit feeding the grid. We expect to bring 
another unit back overnight (Sunday) and the fifth by Wednesday this week,” 
the report said.

Thermal power stations in Bulawayo, Harare and Munyati are also constrained 
in maintaining modest outputs due to the availability of coal from 
suppliers.
“All three suppliers assure us that their production will improve over the 
next two months. Should this not be the case we will have to consolidate and 
probably run only two of the three stations,” added the report.

Major retrofitting and component replacement projects will continue over the 
next 12 months, the report said.

Wapcos, the Indian company that provides expert advice at Hwange, have 
provided an experienced project manager to help oversee these projects at 
Hwange.

ZPC   hopes the execution of these projects would extend planned outages of 
units on a sequential basis next year.

“For example the precipitators (ash handling) on Phase Two will be 
retrofitted over the next seven months therefore from the middle of October 
until May 2012 and one of the Phase two Units will be offline,” said report.

“At Kariba the system that governs the turbine blades, in sympathy to the 
power demand, will be replaced on each unit (six weeks per unit) on a 
sequential schedule. This means that from mid-December until September 2012 
only five of the six units will be online.”

In addition, ZPC will over the next 12 months some units will also be taken 
off line for shorter periods to undertake unit specific upgrades or repairs, 
the report added.

“So in summary the power supply regime will for the next 12 months will be 
much the same as it has been for the last 12 months – all in a bid to 
stabilise and optimise supplies in the medium term,” the report added.

The refurbishment of the 40km pipeline from the Zambezi to the Hwange 
station remains a priority and is a one year project. The feasibility study 
was completed over two months ago and we await the outcome of possible of 
government-to-government funding with the government of India.

While demand for electricity is picking, nothing can be done to augment 
output for the next four years when planned power projects come on board.

Facebook
Twitter
LinkedIn
WhatsApp

107MW solar plant for Hwange

107MW solar plant for Hwange   12/7/2019 The Chronicle Pride Mahlangu, Business Reporter INDEPENDENT power producer, Power Ventures (Private) Limited, has applied for a licence

Read More »

New Posts:

From the archives

Posts from our archive you may find interesting