Why we’re stuck in the dark
http://www.kubatanablogs.net/kubatana/?p=8505
Don’t know about you but 16 hour long power cuts are starting to get me
down. This update from the Zimbabwe Power Company helps to explain the
current spate of bad power:
It is with regret that I advise of the fact that we (Zimbabwe Power
Company) lost the four producing units at Hwange Power Station yesterday
afternoon (Wednesday 25th April). One unit was brought back onto the grid
last night and we hope to bring a second, larger unit, back around 4am
tomorrow (Friday 26th April). Repair on the third unit is scheduled for
completion such that it will be ‘returned to service’ on Saturday morning.
Two phase one (smaller) units are having their rotors re-wired in South
Africa – this is major work.
Kariba has five units on line with the sixth due back on the grid in
mid-May after routine, but critical, maintenance ahead of winter.
The Hwange and Kariba expansion plans remain on program at this time.
The tenders are out and close in June. this will be followed by 2 three
month periods for tender review and finalisation of funding/award.
Thereafter construction will take between three to four years (2016-17).
R. Maasdorp
Chairman ZPC