THE government would have to pay more than US$300 million to complete its
proposed takeover of the Green Fuel ethanol project, sources close to the
company have insisted.
Agriculture Minister Joseph Made announced Monday that the government had
taken over majority control of the US$600 million project in line with the
country’s economic empowerment laws.
But in a statement the company insisted that: “The shareholding of the three
companies (involved in a project) is currently held by Zimbabweans.”
Sources close to the company said if Made insists on pushing through the
takeover, the government would have to pay more than US$300 million for the
51 percent shareholding.
Made claimed the 20-year Build, Operate and Transfer agreement between
agricultural parastatal Arda and two private companies involved in the
project was illegal.
“Cabinet concluded that the BOT agreement signed between Arda and Green
Fuel and other partners was null and void as it has not been authorised by
Government through Cabinet,” Made said.
But in a statement, Green Fuel said the BOT deal did not involve the ethanol
plant at Chisumbanje and only related to the Arda lands on which the
parastatal and its joint venture partners, Rating Investments and Macdom,
were growing sugar cane.
“Green Fuel is a standalone private company built on land leased directly
from the Chipinge Rural District Council in order to facilitate easy access
to the cane grown on the estates of Rating and Macdom,” the company said.
“Green Fuel’s core business is to buy sugar cane from Rating, Macdom and
other growers for processing into sugar or ethanol. Green Fuel has not, nor
has it ever, had a contractual relationship with Arda.”
The company also denied Made’s claim that its agreement with Arda was
irregular adding the Minister was kept abreast of developments from the time
the project was initiated.
“The B.O.T agreements between Arda and the two agricultural companies,
Rating and Macdom, were entered into in compliance of the Agricultural and
Rural Development Authority (ARDA) Act,” the company said.
“They were approved by the Arda Board and signed on the 19th of March 2009
by Arda’s General Manager in terms of Section 17 of the said Act.
“There is correspondence between Arda and its parent ministry of
Agriculture, Mechanisation and Irrigation Development indicating that the
Minister was involved in, and kept abreast of, all the negotiations and
legal formalities leading to the finalization of the B.O.T agreements.
“Finances were raised towards the cane projects on the strength and basis of
the agreements which have been verified as legally valid and binding by
independent legal experts.”
The company has since suspended production at the Chisumbanje mill after
exhausting storage capacity. Efforts to get the government to endorse
mandatory blending of petrol and ethanol have so far been unsuccessful while
market uptake of the company’s E10 product remains limited.
An independent energy analyst warned: “This shift of policy from active
support to complete takeover could jeorpadise the whole investment vision
which presents five thousand jobs now with a potential to reach 10 000 at
full commissioning of the project.
“While ministers haggle over the Green Fuel project, events on the ground at
Chisumbanje are increasingly disconcerting. Green Fuel has sent home some
hundreds of workers due to the slow ethanol sales.
“Oil companies are reportedly indicating they cannot stock E10 in most of
their garages because there is no additional storage, hence the product
glut, but this could also be symptomatic of cartel behavior which is typical
of the oil sector.”